Research project critical path

Calculate earliest starts, latest starts and slack from task durations and dependencies.

Your entries stay in this page’s memory and are not submitted to us. Downloads are generated locally. Reloading or leaving the page clears your entries. Do not enter patient information.

Use unique simple task labels, positive durations in one unit and explicit prerequisites. Maximum 50 tasks. Tasks without predecessors use a hyphen. This assumes unlimited resources and finish-to-start dependencies.

The starting values are hypothetical. Results update as you edit. Use aggregate or synthetic inputs only.

Calculation results

Project duration
15
Critical tasks
protocol, ethics, pilot
Task: earliest start / finish / slack
protocol: 0 / 3 / 0 | ethics: 3 / 13 / 0 | code: 3 / 8 / 5 | pilot: 13 / 15 / 0

How to interpret the output

Critical-path analysis propagates longest prerequisite durations forward and latest allowable starts backward. Zero-slack tasks constrain the stated project duration. Estimates are deterministic; holidays, shared staff, uncertainty and approvals are not modeled. Slack is not permission to miss a deadline.

Method reference

Source checked 2026-11-06. Read the reproducible calculator validation report.